What 41,000 LA ADU Permits Show.

Analysis of 41,450 City of Los Angeles ADU permits since 2020: median size, declared valuation and time to permit and CofO by year, type and area.

Last reviewed 1 source 6 min read

A house in Los Angeles
Photo: This Old House - Los Angeles House Project by Charles & Hudson, CC BY-SA 2.0, via Openverse (flickr).

The short version

  • The City of Los Angeles issued 41,450 ADU permits from 2020 through early November 2026 in the data we analyzed.
  • The typical ADU permit lists about 558 square feet and a declared valuation of $60,000, or about $105 per square foot.
  • The typical permit took 154 days from submission to issue, and 368 more days to reach a certificate of occupancy (CofO) for permits that got that far.
  • Declared valuation is not what an ADU costs to build. Read the limits section before you use any figure here.

Where the numbers come from

Every figure on this page comes from the LADBS "Building Permits Issued 2020 to Present" dataset on the city's open data portal (dataset pi9x-tg5x), which covers the City of Los Angeles only. We identified ADU permits by the permit's ADU flags and descriptions, dropped supplemental permits, and ended with 41,450 permits. All values below are medians, which means half of the permits fall above the number and half below. Our analysis, November 2026. For what an ADU project really involves, see ADU cost in Los Angeles and the ADU timeline guide.

Citywide totals

MeasureCitywide median or count
ADU permits issued41,450
Permits that reached a CofO26,170
Size on the permit558 sq ft
Declared valuation$60,000
Declared valuation per sq ft$105
Days from submission to permit issue154
Days from permit issue to CofO368

About 63 percent of permits in the data show a CofO. Recent permits have not had time to finish.

By year

YearPermitsMedian sq ftMedian declared valueValue per sq ftDays to permitDays permit to CofO
20203,422500$37,000$81124397
20215,148500$45,000$97180428
20227,253554$60,000$105182432
20236,345584$65,000$109173398
20246,615575$70,000$109154347
20257,135582$75,000$111126276
20265,532597$80,000$115134164

Three patterns stand out. First, permit counts rose from 3,422 in 2020 to 7,253 in 2022, dipped to 6,345 in 2023, and then recovered to 7,135 in 2025. Second, the median declared value climbed every year, from $37,000 in 2020 to $80,000 in 2026, while median size moved only from 500 to 597 square feet. Third, the median wait for a permit fell from 182 days in 2022 to 126 days in 2025.

Be careful with the last two columns. The permit-to-CofO figure for recent years only includes projects that already finished, so it only reflects projects that finished. The 2026 figure of 164 days rests on just 444 finished permits out of 5,532, and 2026 is a partial year. Do not read it as proof that building got faster.

By type

TypePermitsMedian sq ftMedian declared valueValue per sq ftDays to permitDays permit to CofO
New construction9,262813$120,000$119213427
Conversion26,461496$50,000$98145358
JADU4,040400$35,000$9289278
Other or unclassified1,687576$75,000$113147389

Medians differ more by type than by year. New construction permits are the largest and most expensive on paper, at 813 square feet and $120,000, and they also take the longest: 213 days to permit and 427 more to a CofO. Conversions, which turn existing space such as a garage into a unit, are the bulk of the data at 26,461 permits, or about 64 percent. Junior ADUs (JADUs), which are carved out of an existing bedroom or part of the house, are the smallest at 400 square feet and the fastest to permit at 89 days. To decide which route fits a lot, read ADU vs JADU vs garage conversion.

Other: ADU permits that are not new buildings, garage or space conversions, or JADUs, mostly additions and alterations that add an ADU.

Top 15 neighborhood council areas by permits

Neighborhood council areas are the city's own geographic labels, and they are not the same as the neighborhood names people use in daily life. The table ranks areas by permit count. 978 permits have no neighborhood council area on record and are left out of the ranking.

RankNeighborhood council areaPermitsMedian sq ftMedian declared valueDays to permitDays permit to CofO
1Reseda1,410575$60,000120307
2Woodland Hills-Warner Center1,241524$55,000123324
3Van Nuys993639$60,000140335
4West Hills917460$50,00090295
5Winnetka903480$50,000107322
6Sylmar883566$50,000133372
7Granada Hills South880600$60,000119328
8Sunland-Tujunga864563$60,000148362
9Greater Valley Glen856593$55,000130379
10NoHo818630$65,000175411
11Pacoima803600$54,500136326
12Sherman Oaks802495$60,000142394
13Lake Balboa777581$60,000125350
14Mar Vista760488$64,426152379
15North Hollywood Northeast690758$75,000147374

Most of the top 15 are Valley neighborhoods. Spread among areas is real but modest in the middle of the table: median days to permit run from 90 to 175 across these 15 areas, against a citywide 154. Areas with few permits have unstable medians, and we show no figure where a group has fewer than 5 permits.

How to use these numbers

  • As a reality check on size: if a design is far from 558 square feet, you are outside what most permits show, which is fine, but expect the cost and schedule to move with it.
  • As a floor for the conversation, not a budget. A declared value of $60,000 is a figure on a form. Ask any builder for a written bid covering design, permit fees, utility work, site work and finishes.
  • As a schedule range: plan for months to a permit and most of a year more to finish, and treat the CofO step as the one that varies most.
  • Use the permit process guide to see what happens between submission and issue.

Method and limits

  • Source. LADBS "Building Permits Issued 2020 to Present" (data.lacity.org, dataset pi9x-tg5x). City of Los Angeles only. Other cities and unincorporated county areas are not included.
  • Finding ADUs. We matched permits by the ADU flags and descriptions in the record. Some ADUs may be missed and some non-ADU permits may be included. Supplemental permits were dropped so one project is not counted twice.
  • Declared valuation. This is the value the applicant wrote on the permit. It is not the full project cost. Design, fees, utilities and finishes are often extra, and applicants may state a value that does not match the final bill. Valuation per square foot inherits the same problem.
  • Times. Medians from submission to issue, and from issue to CofO, only for permits that reached that step. Permits still in progress are not counted, which pulls recent-year times down.
  • Partial year. 2026 runs only through early November, so its permit count is not comparable with a full year.
  • Permit year. Years refer to the permit record in the dataset, not the date construction began or ended.
  • Rounding. Medians are rounded as published in the dataset.
  • Not advice. This is general information, not legal, financial or construction advice. Rules and fees change. Confirm details with LADBS and get written bids before you budget. Pick a builder with care, using hiring an ADU builder and checking a CSLB license.

Source: LADBS "Building Permits Issued 2020 to Present", data.lacity.org dataset pi9x-tg5x (City of Los Angeles only), our analysis, November 2026.